NDPHC: We are committed to ‘Light Up Nigeria’ despite challenges

Oyindamola Akanni
Oyindamola Akanni
Ugbo

The Niger Delta Power Holding Company Limited, NDPHC, has declared its commitment to light up Nigeria despite the challenges facing it.

The commitment was declared on Monday in Lagos by the Managing Director/Chief Executive Officer of the company, Mr. Chiedu Ugbo, during a “Light up Nigeria” campaign.

He described as one of the challenges facing the company, the about N190 billion it is being owed.

According to him, the non-payment of the debt had so far negatively affected the speed at which the company would have improved power services in the country.

He said, however, that the company would continue with the goal to “Light Up Nigeria.”

His words: “There is also low invoice payment for energy generated to the grid. There is huge indebtedness by the market to NDPHC in hundreds of billions for unpaid invoices. NDPHC is also not paid for availability but only as dispatched thereby depriving NDPHC of hundreds of billions since 2015 when transitional electricity market (TEM) was declared.”

Noting that NDPHC also owed some stakeholders, Ugbo said the federal government under President Bola Tinubu had taken a soft and citizens-oriented approach by not increasing tariffs but assured that it would find a way to address the shortfalls in payment as per the actual consumption and the tariff.

READ ALSO: WASSCE: WAEC adopts CBT, announces commencement date

Ugbo added: “To reasonably resolve the challenges to power plants’ operations and increase electricity supply to homes and businesses, NDPHC’s Light-up Nigeria initiative is to explore not only the opportunities under the Eligible Customer Regulations and Electricity Act 2023 but also bilateral power sales in collaboration with Discos and other bulk purchasers under trading arrangements will ensure that investment is mobilized for end-to-end solutions that will guarantee that electricity is delivered to customers and NDPHC is paid for the electricity generated.

“At the core of NDPHC’s initiatives is to prioritise high-value power sale opportunities with bulk purchasers and Discos, which under Nigerian Electricity Supply Industry (NESI) have significant power supply demands across their franchise areas. The rationale for this approach is that projects delivered in collaboration with these potential bulk purchasers are likely to generate significantly greater volumes of power sales under bankable arrangements.”

He stated that the NDPHC was the implementing entity for the National Integrated Power Project, NIPP.

He noted that NDPHC commenced the design and development of 10 NIPP power plants in 2006.

Eight of the power plants, according to him, had since been completed and were mostly operational.

Two (Egbema and Omoku), he said, were yet to be commissioned.

Alaoji’s gas turbines (4 units), according to him, had been commissioned while its steam turbine was under construction.

He stated that the achievements of NDPHC’s operations were hampered by a number of systemic challenges which had significantly affected its cash flow but which put differently presented good private investment opportunities.

According to him, the challenges also presented opportunities for investments.

On the transmission constraints, he identified inadequate transmission and distribution grid capacity to evacuate energy generated from the power plants as a challenge.

He noted that in 2022, transmission and distribution available capacity was estimated at about 5,500MW.

He, however, said that NDPHC was currently allocated a maximum dispatch space of 975MW (peak period) and 757MW at off-peak (despite often substantially mechanically available).

Ugbo said: “Talking more about constraints, evacuation limitation is further exacerbated by systems operations frequent start-up and shut down instructions to the plants ostensibly for frequency and load control to ensure system safety and reliability, but resulting in increased turbine stress, more unscheduled outages and significant maintenance costs.

“Another challenge is gas supply and transportation constraints. There is unavailability of sufficient volumes of gas to guarantee generation up to Transmission Company of Nigeria (TCN) allocated evacuation capacity of 975MW let alone full capacity of its power plants.

“Calabar is the only plant with full gas supply. Plants in western axis require about 150MMSCF/day to meet TCN-allocated evacuation capacity 535MW (Peak).

“Gas supply to western axis power plants is further challenged by low pressure on NGIC gas pipelines –ELPS & Oben-Ajaokuta. Gas suppliers want higher gas tariff beyond industry approved gas tariff ($2.50 vs. $2.18).”